Studio Construction - Day 12 - North and South Girder Alignment and Bolting @vk2zay
Studio Construction - Day 12 - North and South Girder Alignment and Bolting  @vk2zay
Uploaded February 2023 | Updated November 2026, 3 hours ago
Freezing day after a particularly cold night. Interrupted by the power pole at the corner of my driveway falling over onto the road and taking out power and data wiring to my and adjacent properties!

In better news the nailgun is finally cooperating! Finished middle girder lamination in-place (not filmed). Aligned and bolted the north and south girders to the pier brackets. Checked middle girder level, unacceptably terrible! Center pier is high enough that the girder can rock about 2 inches high at one end. All the other piers are fine. Not a situation that can be shimmed out. Will have to chip out concrete from the pier and trim j-bolt slightly to align and level properly.

Spent a bit of time after power pole distraction cutting up and dragging downed trees to the waste pile. This will give me a better location for the camera as we progress to non-foundation work on the studio, and in general clean the yard up a bit - still a giant mess though.
Studio Construction - Day 12 - North and South Girder Alignment and BoltingAdvent Calendar of Circuits 2011: Day 3:  Metal DetectorUsing a Ceramic Capacitor as a Hydrophone TransducerPermeability of different materialsStudio Construction - Day 40 - Dormer Cheek Wall LayoutSenko Hanabi Sparkler240 LED Animated PWM-controlled Christmas TreeHand-Feeding Wild Rainbow Lorikeets17 LED Chaser (Larson Scanner Bit-Shift Software)Studio Construction - Day 01 - Pier hole diggingAdvent Calendar of Circuits 2011: Day 6: Coils For The SnifferAdvent Calendar of Circuits 2011: Day 21: Forever Flasher
Alan Yates |

Studio Construction - Day 12 - North and South Girder Alignment and Bolting

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER