Studio Construction - Day 01 - Pier hole digging @vk2zay
Studio Construction - Day 01 - Pier hole digging  @vk2zay
Uploaded February 2023 | Updated November 2026, 3 hours ago
Time to mark out the 15 pier locations and start digging them.

Universal rule of construction; start digging a foundation and it will rain. Also, your site will be on a field full of potato to head-sized rocks and you will hit a mysterious buried object that is impenetrable and seemingly edgeless!

Hard going; started with Violet having destroyed the string lines in the early morning. I had marked the batter boards so this was relatively easy to fix. Layout and marking of the 1st 10 of the 15 pier locations went easily once I untangled the lines and rolled them up out the way for future form work and J-bolt alignment.

Digging the pier holes however was a bit of a disaster. The site is absolutely jam packed full of medium sized river stones, from potato sized to much larger. This is extremely annoying to bore into with the auger, it makes it kick hard when you hit one and I am still sore from levering and lifting them out of the holes with a digging bar and post manual hole digger. About 1 meter down below grade I hit something hard, basically impenetrable and apparently large enough that all the holes I dug hit it. I have to work out what it is before I can continue, it is not on any maps of the site I consulted before starting the project. It shouldn't be bedrock here, it isn't a pipe or drain-field, and it doesn't look like concrete. I am at a bit of a loss as to what it actually is?
Studio Construction - Day 01 - Pier hole diggingAdvent Calendar of Circuits 2011: Day 6: Coils For The SnifferAdvent Calendar of Circuits 2011: Day 21: Forever FlasherStudio Construction - Day 17 - Floor InsulationFerroelectric Behaviour in PZT Capacitor DielectricsSinusoidal Blink PWMDay 11 Extra: Wavemeter SensitivityStudio Construction - Day 10 - Middle Girder PlacementBiasing Inductor SaturationACoC 2025: Day 8: Dim Bulb TesterBottle Rocket with Glitter StarsQuartz Super-regenerative Remote Control Transceiver Testing Loop