Uploaded April 2024 | Updated November 2026, 2 days ago
👇 Drop your answers in the comments! FULL VIDEO available on YouTube with the answer and explanation!
🔍 Scenario: After securing the site, the developer has provided the zoning ordinance and site information to the architect. The developer has asked the architect to provide a feasibility report and include information regarding unique considerations for this site. The developer intends to use this feasibility report to inform the project program, schedule, and budget.
What unique considerations should the architect include in this report? Select the four that apply.
A. Presence of chemical waste
B. Increase in FAR if retail is provided along Peter Street
C. Project must be LEED Silver equivalent
D. Proximity to the coastline
E. Majority office program not permissible
F. Must hold three public comment periods
👇 Drop your answers in the comments! FULL VIDEO available on YouTube with the answer and explanation!
🔍 Scenario: After securing the site, the developer has provided the zoning ordinance and site information to the architect. The developer has asked the architect to provide a feasibility report and include information regarding unique considerations for this site. The developer intends to use this feasibility report to inform the project program, schedule, and budget.
What unique considerations should the architect include in this report? Select the four that apply.
A. Presence of chemical waste
B. Increase in FAR if retail is provided along Peter Street
C. Project must be LEED Silver equivalent
D. Proximity to the coastline
E. Majority office program not permissible
F. Must hold three public comment periods








![PjM Practice Exam Question #shorts #architecture
A project manager is meeting with the principal of their firm and is told that a new hire is going to be assigned to their project team. The project manager takes the following notes at the meeting:
● New Hire’s Salary: $110,000
● 3-weeks paid time off (PTO)
● Firm’s net multiplier: - 3.50
What billable rate should be used for the new employee? Round to the nearest $5.
A. $185 per hour
B. $195 per hour
C. $55 per hour
D. $110 per hour
💡Answer: A [$185 per hour]
📍Answer Breakdown: $110,000 / 2,080 hours per year * 3.5 = $185 per hour PjM Practice Exam Question #shorts #architecture](https://i.ytimg.com/vi/_gq70dDWymY/mqdefault.jpg)