The principal of a 6-person firm is responding to an RFP for a new high-school gymnasium and sports field addition. The high school is a locally designated landmark and the addition will include an extension onto the rear of the building, as well as a new field house. The school district emphasized in their RFP materials that the budget is tight and that the duration allotted for the project’s design is 8 months.

Which of the following should the principal highlight in their RFP response? Check the three that apply.

A. Staff resumes demonstrating experience on educational projects.
B. The firm’s extensive experience on historic renovation projects.
C. A preliminary rendering of the firm’s vision for the project.
D. A guarantee that the construction cost will not exceed the client’s budget.
E. Recently completed athletic facility projects.
F. A proposed five month design schedule.

💡Answer: A, B & E
PcM Practice Exam Question #shortsPjM Practice Exam Question #shorts #architectureARE Live: Project Development & Documentation Exercise | ARE 5.0 PDD ExamHow Black Spectacles Practice Exams Explain Correct & Incorrect AnswersWhy Licensure Matters? #shortsPjM Practice Exam Question #shorts #architectureProject Development & Documentation Mock Exam Question #4 | ARE 5.0 PDD Mock Exam #architectureProject Planning & Design Mock Exam Question #2 | ARE 5.0 PPD Mock Exam #architecture #podcastPDD Practice Exam Question #shortsCSE Live: How to Become a Licensed Architect in CaliforniaARE Live: Practice Management Mock Exam | ARE 5.0 PcM Exam 2024CSE Practice Exam Question #shorts #architecture