The architect receives a plan check comment from the local fire department that asks to relocate the fire lane away from large existing trees. The proposed path routes through a sensitive habitat for a local endangered animal species. What should the architect do?
A. Reroute the fire lane through the sensitive habitat
B. Explain to the fire department that the fire lane cannot be rerouted due to the sensitive habitat
C. Schedule a meeting with the local fire department and Cal EPA to discuss
D. Have the owner hire a zoologist to confirm the presence of the animal species.
đź’ˇAnswer: C
The architect receives a plan check comment from the local fire department that asks to relocate the fire lane away from large existing trees. The proposed path routes through a sensitive habitat for a local endangered animal species. What should the architect do?
A. Reroute the fire lane through the sensitive habitat
B. Explain to the fire department that the fire lane cannot be rerouted due to the sensitive habitat
C. Schedule a meeting with the local fire department and Cal EPA to discuss
D. Have the owner hire a zoologist to confirm the presence of the animal species.
đź’ˇAnswer: C