A project manager is delegating submittal reviews to their project team for a new construction cast-in-place concrete high-rise project that just completed the foundation phase of the project. At a recent Owner-Architect-Contractor (OAC) meeting, the contractor noted that the project will proceed immediately into the superstructure phase.

Which of the following submittals should the project manager ensure is reviewed this week? Check the three that apply.

A. Rebar accessories product data
B. Concrete formwork layout
C. Temporary shoring shop drawings
D. Elevator hoistway layout
E. Tower crane concrete embedment shop drawing
F. Curtain wall concrete embedment shop drawing

💡Answer: A, D & F
PjM Practice Exam Question #shorts #architectureARE Live: Project Development & Documentation Exercise | ARE 5.0 PDD ExamHow Black Spectacles Practice Exams Explain Correct & Incorrect AnswersWhy Licensure Matters? #shortsPjM Practice Exam Question #shorts #architectureProject Development & Documentation Mock Exam Question #4 | ARE 5.0 PDD Mock Exam #architectureProject Planning & Design Mock Exam Question #2 | ARE 5.0 PPD Mock Exam #architecture #podcastPDD Practice Exam Question #shortsCSE Live: How to Become a Licensed Architect in CaliforniaARE Live: Practice Management Mock Exam | ARE 5.0 PcM Exam 2024CSE Practice Exam Question #shorts #architectureProject Development & Documentation Mock Exam Question #1 | ARE 5.0 PDD Mock Exam  #architecture
Black Spectacles |

PjM Practice Exam Question #shorts #architecture

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER