On today's ARE Live broadcast, Thursday, January 20, 2022 at noon CT, we’ll run through an exercise from one of our Virtual Workshops with Instructor Marissa Yee. She’ll review a few Project Development & Documentation practice questions focused on the integration and documentation of building systems, material selection, and material assemblies into a project.
Learn more about Black Spectacles ARE 5.0 exam prep here: blackspectacles.com/pricing.
On today's ARE Live broadcast, Thursday, January 20, 2022 at noon CT, we’ll run through an exercise from one of our Virtual Workshops with Instructor Marissa Yee. She’ll review a few Project Development & Documentation practice questions focused on the integration and documentation of building systems, material selection, and material assemblies into a project.


![PjM Practice Exam Question #shorts #architecture
A project manager is meeting with the principal of their firm and is told that a new hire is going to be assigned to their project team. The project manager takes the following notes at the meeting:
● New Hire’s Salary: $110,000
● 3-weeks paid time off (PTO)
● Firm’s net multiplier: - 3.50
What billable rate should be used for the new employee? Round to the nearest $5.
A. $185 per hour
B. $195 per hour
C. $55 per hour
D. $110 per hour
💡Answer: A [$185 per hour]
📍Answer Breakdown: $110,000 / 2,080 hours per year * 3.5 = $185 per hour PjM Practice Exam Question #shorts #architecture](https://i.ytimg.com/vi/_gq70dDWymY/mqdefault.jpg)