Plumbers first measure and mark pipe placements – The plumbers start with a set of plans, and measure precisely the locations for your fixtures (sinks, tubs, toilets), stacks (main pipes), and walls (so they can hide pipes within). They mark these measurements on the wood form boards that will eventually contain the concrete poured to create your foundation

Plumbers dig trenches– Once the plumbers know where to run their lines, they roll out a small trench-digger and dig trenches for the main lines. If they run into hard rock beneath the surface, as we saw in the home site we featured, they’ll have to roll out a back-hoe for some serious digging.

Plumbers run sewer lines – Once the trenches are dug, the plumbers run PVC pipe to create the drainage system for your house. They rely on gravity to drain sewage away from the house, so all lines run at a slight downward angle from the house to properly drain into the sewer lines.

Plumbers loop copper water lines – They use soft, bendable copper tubes so no joints exist within the concrete. Then they solder them shut above the eventual level of your foundation slab. They place a blue sleeve around cold water lines, and red sleeves around hot water lines. When concrete comes in contact with metal, it creates a chemical reaction called electrolysis that could eventually eat away at the copper tubing.
So in addition to identifying hot and cold lines, the sleeves protect the sections of the copper tubing that will eventually be encased in concrete to make sure the copper never actually touches the concrete and sets off this reaction.

Plumbers dig & connect to city sewer & water lines – They call these yard lines or service lines. This is the stage where they tie in to the main lines provided by the city and the developer. One line feeds water into your house; the other line drains water & sewage away from your house into municipal sewer lines.

Pressure testing – The plumbers will “stub out” the pipes so they stick out at least 4 feet above the eventual level of foundation concrete. Different regions utilize different pressure tests, but the goal is the same. They want to make sure before they encase all this plumbing work in concrete that none of your pipes will leak.

Water Test – First they tap into your main water line and fill all your pipes with water. The 4 feet of vertical water in the pipes will create a gravitational pressure in the system of still-exposed pipes. About a day later, an inspector will check for leaks and wet spots on the ground.

Air Test – In this approach, the plumbers will seal off all pipes and pump air into the system to create a specific pressure level. A day or two later, inspectors will measure the remaining pressure, compare it to the initial pressure and determine if the system contains any leaks that must be plugged before your foundation is poured.

Critical Points for Homeowners – You may not get directly involved in the ground plumbing process, but a lot of your decisions and desires will have a direct affect on the ground work the plumbers do as they start to work on your house. The plumbers must be precise when they place pipes and fixtures, because most of their work needs to be hidden inside the walls of your house, which are usually no thicker than 6 inches. If you’re building a home, you need to think now about how many sinks and tubs and toilets you want, and exactly where you want them in the kitchens or bathrooms.

We featured a home site which will include a free-standing island in the kitchen, complete with a sink. That’s a great amenity, but it means that the sink will not be attached to a wall, as most sinks are. So the plumbers have to run special lines just for that sink that’ll run down into the floor, over to the nearest wall, then up and out like the other fixtures. You can see why planning ahead is so crucial.

If you’re thinking about a wet bar in a family room, decide now, or else you’ll spend a ton of money digging up the concrete to re-route the plumbing after the house is built to accommodate that wet bar. What kind of bathtubs will you have in the bathrooms? Which end will they drain from? Or do you want to get one of those nice big tubs that drain from the middle? The answer determines where the plumbers place your fixture connections now, so you need to make those decisions now. If the plumbers design a drainage system in your bathroom for a standard tub (the kind that drains from one end or the other), and you’ve got your heart set on a spa tub with a drain in the center, then the drainage connection will be off by a few crucial inches.

Once the system passes the pressure test, the entire network of piping is covered with sand and dirt to cushion the pipes from the weight of the concrete that will encase them.
Plumbing Rough: Renaissance Project House - Part 2AHow to Build a Vegetable Garden Complete - The Great OutdoorsDo You Need House Wrap? - Adventures in HomebuildingInstalling a French Drain - Fix It UpClever ways to hang pots and bird feeders - The Great OutdoorsMega Build -16,000 sf - Part 19: Ceramic SurfacesGutter Alternative: Rainhandler - Do It YourselfDIY Vine Pole & Plant Stand - The Great OutdoorsShellac - Quick TipFloor Sanding Mistakes: Refinishing Hardwoods - Fix It UpReplacing an Attic Fan - Do It YourselfHow to Texture a Wall (7 options) Do It Yourself
Your New House |

Plumbing Rough: Renaissance Project House - Part 2A

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER