The contractor for a new construction industrial building has fallen behind the construction schedule. The owner is concerned that the contractor doesn’t have a plan to get back on track, and asks the architect to assist in any way that they can so the project can be completed by the originally scheduled date. The owner is open to pay the architect for additional services if they feel that the service can get the project’s schedule corrected. What can the architect suggest to the owner to help get the project back on track?
A. Daily site visits and field reports from the architect to keep the owner informed of progress.
B. Construction scheduling services to determine the critical path.
C. Prioritization of submittals and RFIs as directed by the contractor.
D. Means and methods review by the architect to determine alternate construction sequences.
💡Answer: C
The contractor for a new construction industrial building has fallen behind the construction schedule. The owner is concerned that the contractor doesn’t have a plan to get back on track, and asks the architect to assist in any way that they can so the project can be completed by the originally scheduled date. The owner is open to pay the architect for additional services if they feel that the service can get the project’s schedule corrected. What can the architect suggest to the owner to help get the project back on track?
A. Daily site visits and field reports from the architect to keep the owner informed of progress.
B. Construction scheduling services to determine the critical path.
C. Prioritization of submittals and RFIs as directed by the contractor.
D. Means and methods review by the architect to determine alternate construction sequences.
💡Answer: C