An architect is working with a restaurateur to design a new construction food court in a downtown, commercially zoned area. The owner has built several freestanding restaurants before, but never a project of this scope.
Which of the following should the project team consider at the onset of the project? Check the three that apply.
A. Verify that the proposed use is permitted in the zoning district.
B. Determine egress capacity.
C. Conduct a traffic study.
D. Determine the building’s structural system.
E. Conduct a programming study.
F. Develop conceptual facade designs.
💡Answer: A, C & E
An architect is working with a restaurateur to design a new construction food court in a downtown, commercially zoned area. The owner has built several freestanding restaurants before, but never a project of this scope.
Which of the following should the project team consider at the onset of the project? Check the three that apply.
A. Verify that the proposed use is permitted in the zoning district.
B. Determine egress capacity.
C. Conduct a traffic study.
D. Determine the building’s structural system.
E. Conduct a programming study.
F. Develop conceptual facade designs.
💡Answer: A, C & E