The preliminary bids for a new-construction school building are over budget at the end of the design-development phase of the project. The design specifies a brick facade that costs $28 per square foot. The owner wants to maintain the appearance of masonry but is open to alternative materials to reduce costs. The construction manager advises that the masonry facade is 30,000 square feet, and proposes the following alternates:

1. Thin brick panel system: $18 per square foot
2. Architectural precast concrete panels: $22 per square foot
3. Fiber cement panels: $12 per square foot

What are the cost savings of switching to the preferred alternative façade material?

A. $180,000
B. $300,000
C. $480,000

💡Answer: B
📍Answer Breakdown: ($28/sf. - $18/sf.) X 30,000sf. = $300,000
PPD Practice Exam Question #shorts #architectureProject Planning & Design Mock Exam Question #1 | ARE 5.0 PPD Mock ExamARE Live: Navigating the A201 | ARE 5.0 ExamCE: Coming Soon #shortsARE Live: Construction & Evaluation Mock Exam | ARE 5.0 CE Exam 2025The Money Gap | Is the License Worth It?ARE Live: Project Development & Documentation Mock Exam | ARE 5.0 PDD ExamProgramming & Analysis Mock Exam Question #3 | ARE 5.0 PA Mock Exam #architectureHow Top Architecture Firms Help Employees Pass the ARE 5.0 | Black Spectacles Firm TestimonialProject Management Mock Exam Question #2 | ARE 5.0 PjM Mock Exam #architectureNew Programming & Analysis Available Now!Moxk Exam: Masonry Drainage #shorts
Black Spectacles |

PPD Practice Exam Question #shorts #architecture

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER