The preliminary bids for a new-construction school building are over budget at the end of the design-development phase of the project. The design specifies a brick facade that costs $28 per square foot. The owner wants to maintain the appearance of masonry but is open to alternative materials to reduce costs. The construction manager advises that the masonry facade is 30,000 square feet, and proposes the following alternates:
1. Thin brick panel system: $18 per square foot
2. Architectural precast concrete panels: $22 per square foot
3. Fiber cement panels: $12 per square foot
What are the cost savings of switching to the preferred alternative façade material?
A. $180,000
B. $300,000
C. $480,000
💡Answer: B
📍Answer Breakdown: ($28/sf. - $18/sf.) X 30,000sf. = $300,000
The preliminary bids for a new-construction school building are over budget at the end of the design-development phase of the project. The design specifies a brick facade that costs $28 per square foot. The owner wants to maintain the appearance of masonry but is open to alternative materials to reduce costs. The construction manager advises that the masonry facade is 30,000 square feet, and proposes the following alternates:
1. Thin brick panel system: $18 per square foot
2. Architectural precast concrete panels: $22 per square foot
3. Fiber cement panels: $12 per square foot
What are the cost savings of switching to the preferred alternative façade material?
A. $180,000
B. $300,000
C. $480,000
💡Answer: B
📍Answer Breakdown: ($28/sf. - $18/sf.) X 30,000sf. = $300,000