PjM Practice Exam Question #shorts #architecture @Blackspectacles
PjM Practice Exam Question #shorts #architecture  @Blackspectacles
Uploaded July 2026 | Updated November 2026, 2 days ago
The work plan for a ground-up residential project includes 700 hours of time spent on the schematic design phase. The project team is composed of four employees with an average HOURLY rate of $60 per hour, and the firm’s net multiplier is 3.25. At the end of the SD phase, the project manager realizes that the project team spent 85 more hours on the project during the phase than was accounted for in the work plan.

What is the total cost of these additional hours?

A. $5,100
B. $39,250
C. $127,563
D. $16,575

💡Answer: D
📍Answer Breakdown: $60/hour x 3.25 x 85 hours = $16,575
PjM Practice Exam Question #shorts #architectureARE Live: Project Development & Documentation Mock Exam | ARE 5.0 PDD Exam 2024CE Practice Exam Question #shorts #architecturePPD Practice Exam Question #shorts #architectureARE Live: Construction & Evaluation Mock Exam | ARE 5.0 CE Exam 2024This is the new PcM content! #shortsPDD Practice Exam Question #shorts #architectureProject Management Mock Exam Question #2 | ARE 5.0 PjM Mock ExamPcM Practice Exam Question #shorts #architecture
Black Spectacles |

PjM Practice Exam Question #shorts #architecture

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER