The work plan for a ground-up residential project includes 700 hours of time spent on the schematic design phase. The project team is composed of four employees with an average HOURLY rate of $60 per hour, and the firm’s net multiplier is 3.25. At the end of the SD phase, the project manager realizes that the project team spent 85 more hours on the project during the phase than was accounted for in the work plan.
What is the total cost of these additional hours?
A. $5,100
B. $39,250
C. $127,563
D. $16,575
💡Answer: D
📍Answer Breakdown: $60/hour x 3.25 x 85 hours = $16,575
The work plan for a ground-up residential project includes 700 hours of time spent on the schematic design phase. The project team is composed of four employees with an average HOURLY rate of $60 per hour, and the firm’s net multiplier is 3.25. At the end of the SD phase, the project manager realizes that the project team spent 85 more hours on the project during the phase than was accounted for in the work plan.
What is the total cost of these additional hours?
A. $5,100
B. $39,250
C. $127,563
D. $16,575
💡Answer: D
📍Answer Breakdown: $60/hour x 3.25 x 85 hours = $16,575