An architect is preparing a fee proposal for a private developer client to design a new 20-unit residential project on an urban infill lot. The architect took the following notes during their call with the potential client:

1. Height variance required from planning board
2. Fast-track with construction manager as constructor
3. 24 month construction schedule

Which of the following should the architect consider when preparing their fee proposal? Check the two that apply.

A. Hourly rate for work during the entitlement process.
B. Fixed fee for the entire scope of work.
C. Guaranteeing successful variance request.
D. Charging a premium due to increased liability.
E. Hourly rate for construction contract administration.
F. Excluding construction contract administration.

đź’ˇAnswer: A & D