CE Practice Exam Question #shorts #architecture @Blackspectacles
CE Practice Exam Question #shorts #architecture  @Blackspectacles
Uploaded October 2026 | Updated November 2026, 2 days ago
During the construction of a mid-rise project, the contractor submits several shop drawings to the architect for their review prior to the commencement of superstructure activities. The architect reviews the submittals according to the submittal schedule, but marks several submittals as ‘not reviewed’ because they’re not required by the contract documents. The contractor is delayed by ten days in beginning the superstructure and alleges that the delay is attributed to the lack of review by the architect. How should the situation be resolved?

A. Issue a change order for 10 additional days to be added to the construction schedule.
B. Issue a construction change directive to proceed with the work according to the contract documents.
C. The contractor is responsible for the delay.
D. The owner is responsible for the delay.

💡Answer: C
CE Practice Exam Question #shorts #architecturePPD Practice Exam Question #shorts #architectureARE Live: Construction & Evaluation Mock Exam | ARE 5.0 CE Exam 2024This is the new PcM content! #shortsPDD Practice Exam Question #shorts #architectureProject Management Mock Exam Question #2 | ARE 5.0 PjM Mock ExamPcM Practice Exam Question #shorts #architecture
Black Spectacles |

CE Practice Exam Question #shorts #architecture

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER