An architect is performing contract administration for a project where the owner recently requested that the specified light fixtures in the library be changed to a different type of fixture. The architect and design team have reviewed the change and approve of the new fixtures.
At a recent OAC meeting where this was discussed, the contractor noted that the change will result in an additional charge of $150 per fixture. The owner reminded the contractor that this same change was implemented on a previous project that they worked on together, and the additional charge was only $100 per fixture. The contractor noted that they remember the past project vividly, and that it was three years ago and prices have increased. They also noted that light fixtures are scheduled to be installed in the next two weeks. The owner noted that they wanted to ensure no delay to the project schedule due to this minor change.
How should the architect document this change?
A. Change order
B. Construction Change Directive
C. Minor Change in the Work
đź’ˇAnswer: B
An architect is performing contract administration for a project where the owner recently requested that the specified light fixtures in the library be changed to a different type of fixture. The architect and design team have reviewed the change and approve of the new fixtures.
At a recent OAC meeting where this was discussed, the contractor noted that the change will result in an additional charge of $150 per fixture. The owner reminded the contractor that this same change was implemented on a previous project that they worked on together, and the additional charge was only $100 per fixture. The contractor noted that they remember the past project vividly, and that it was three years ago and prices have increased. They also noted that light fixtures are scheduled to be installed in the next two weeks. The owner noted that they wanted to ensure no delay to the project schedule due to this minor change.
How should the architect document this change?
A. Change order
B. Construction Change Directive
C. Minor Change in the Work
đź’ˇAnswer: B










![PjM Practice Exam Question #shorts
A project manager is meeting with the principal of their firm and is told that a new hire is going to be assigned to their project team. The project manager takes the following notes at the meeting:
1. New Hire’s Salary: $110,000
2. 3-weeks paid time off (PTO)
3. Firm’s net multiplier: - 3.50
What billable rate should be used for the new employee? Round to the nearest $5.
A. $185 per hour
B. $195 per hour
C. $55 per hour
D. $110 per hour
đź’ˇAnswer: A [$185 per hour]
📍Answer Breakdown: $110,000 / 2,080 hours per year * 3.5 = $185 per hour PjM Practice Exam Question #shorts](https://i.ytimg.com/vi/p4NYIo7plBc/mqdefault.jpg)