A project has been determined to require review under CEQA. After review, it is determined that the project indeed has significant environmental impacts. Which of the following would the lead agency prepare first?
A. Environmental Impact Report
B. Notice of Preparation
C. Notice of Completion
D. Notice of Determination
đź’ˇAnswer: B
A project has been determined to require review under CEQA. After review, it is determined that the project indeed has significant environmental impacts. Which of the following would the lead agency prepare first?
A. Environmental Impact Report
B. Notice of Preparation
C. Notice of Completion
D. Notice of Determination
đź’ˇAnswer: B





![PjM Practice Exam Question #shorts
A project manager is meeting with the principal of their firm and is told that a new hire is going to be assigned to their project team. The project manager takes the following notes at the meeting:
1. New Hire’s Salary: $110,000
2. 3-weeks paid time off (PTO)
3. Firm’s net multiplier: - 3.50
What billable rate should be used for the new employee? Round to the nearest $5.
A. $185 per hour
B. $195 per hour
C. $55 per hour
D. $110 per hour
đź’ˇAnswer: A [$185 per hour]
📍Answer Breakdown: $110,000 / 2,080 hours per year * 3.5 = $185 per hour PjM Practice Exam Question #shorts](https://i.ytimg.com/vi/p4NYIo7plBc/mqdefault.jpg)