Uploaded August 2026 | Updated November 2026, 2 days ago
A developer is planning a speculative residential condominium building and wants to maximize floor plate efficiency by minimizing circulation space and maximizing saleable area. The developer has purchased a large, open parcel and is consulting with the architect about different building layout and orientation strategies. Which floor plate configuration is likely to be the most efficient?
A. Single-loaded corridor
B. Double-loaded corridor
C. U-shaped floor plate
D. Atrium-centered floor plate
đź’ˇAnswer: B
A developer is planning a speculative residential condominium building and wants to maximize floor plate efficiency by minimizing circulation space and maximizing saleable area. The developer has purchased a large, open parcel and is consulting with the architect about different building layout and orientation strategies. Which floor plate configuration is likely to be the most efficient?
A. Single-loaded corridor
B. Double-loaded corridor
C. U-shaped floor plate
D. Atrium-centered floor plate
đź’ˇAnswer: B
![PjM Practice Exam Question #shorts
A project manager is meeting with the principal of their firm and is told that a new hire is going to be assigned to their project team. The project manager takes the following notes at the meeting:
1. New Hire’s Salary: $110,000
2. 3-weeks paid time off (PTO)
3. Firm’s net multiplier: - 3.50
What billable rate should be used for the new employee? Round to the nearest $5.
A. $185 per hour
B. $195 per hour
C. $55 per hour
D. $110 per hour
đź’ˇAnswer: A [$185 per hour]
📍Answer Breakdown: $110,000 / 2,080 hours per year * 3.5 = $185 per hour PjM Practice Exam Question #shorts](https://i.ytimg.com/vi/p4NYIo7plBc/mqdefault.jpg)