A materials supplier has furnished materials for a commercial project and sent a notice of lien rights to the owner. After some time, the materials supplier still has not gotten paid by the contractor and would like to file a lien on the property. At the architect’s recommendation, the Owner has filed a notice of completion for the project.

How many days from substantial completion does the materials supplier have to file the lien?

A. 30 days
B. 60 days
C. 90 days
D. Materials suppliers are not eligible for design professionals’ liens

💡Answer: A
CSE Practice Exam Question #shorts #architecturePractice Management Mock Exam Question #3 | ARE 5.0 PcM Mock Exam #architectureProgramming & Analysis Mock Exam Question #1 | ARE 5.0 PA Mock Exam #architectureCE Practice Exam Question #shortsARE Live: What to Do on Your Site Visit | ARE 5.0 ExamARE Live: How to Become a Licensed Architect in 2025Project Development & Documentation Mock Exam Question #3 | ARE 5.0 PDD Mock Exam #architectureSpectacular Firm Career Showcase 2024 | Connect with Top Architecture FirmsCE Practice Exam Question #shorts #architectureARE Live: ARE Testing Tips for ESL Candidates | ARE 5.0 ExamARE Live: Zoning Ordinances | ARE 5.0 ExamThe Art Building Strategy #shorts
Black Spectacles |

CSE Practice Exam Question #shorts #architecture

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER