During the construction of a mid-rise project, the contractor submits several shop drawings to the architect for their review prior to the commencement of superstructure activities. The architect reviews the submittals according to the submittal schedule, but marks several submittals as ‘not reviewed’ because they’re not required by the contract documents. The contractor is delayed by ten days in beginning the superstructure and alleges that the delay is attributed to the lack of review by the architect.

How should the situation be resolved?

A. Issue a change order for 10 additional days to be added to the construction schedule.
B. Issue a construction change directive to proceed with the work according to the contract documents.
C. The contractor is responsible for the delay.
D. The owner is responsible for the delay.

💡Answer: C
CE Practice Exam Question #shortsARE Live: What to Do on Your Site Visit | ARE 5.0 ExamARE Live: How to Become a Licensed Architect in 2025Project Development & Documentation Mock Exam Question #3 | ARE 5.0 PDD Mock Exam #architectureSpectacular Firm Career Showcase 2024 | Connect with Top Architecture FirmsCE Practice Exam Question #shorts #architectureARE Live: ARE Testing Tips for ESL Candidates | ARE 5.0 ExamARE Live: Zoning Ordinances | ARE 5.0 ExamThe Art Building Strategy #shortsARE Live: Project Planning & Design Mock Exam | ARE 5.0 PPD Exam 2024ARE Live: Setting a Study Foundation | Tips for Passing the ARE 5.0CSE Practice Exam Question #shorts #architecture