Richard helped again and we got both remaining walls up and tied in just as the rain started to get heavy.
Built the full-height ridge beam post into the east wall, but otherwise pretty much the same as the west one with the exception of the two fairly large windows. The north wall has a large window placed as in the south wall, and a one smaller 2x3 window.
Probably frame and subfloor the loft next so as to give a nice work platform for framing the west gable which has two small windows, one each side of the ridge beam post. I'll probably build a temporary platform over the cathedral end too for framing the east gable. Then shear sheathing for the walls, ridge beam central post and the big beam itself, and finally rafters and subfacia to pretty much complete the framing... Then of course roofing, siding, trimming, build some stairs, electrical, plumbing, drywall, flooring etc.
Richard helped again and we got both remaining walls up and tied in just as the rain started to get heavy.
Built the full-height ridge beam post into the east wall, but otherwise pretty much the same as the west one with the exception of the two fairly large windows. The north wall has a large window placed as in the south wall, and a one smaller 2x3 window.
Probably frame and subfloor the loft next so as to give a nice work platform for framing the west gable which has two small windows, one each side of the ridge beam post. I'll probably build a temporary platform over the cathedral end too for framing the east gable. Then shear sheathing for the walls, ridge beam central post and the big beam itself, and finally rafters and subfacia to pretty much complete the framing... Then of course roofing, siding, trimming, build some stairs, electrical, plumbing, drywall, flooring etc.