Replace Flooring at VA McClellan - VA Northern California Health Care System, Project 612A4-27-020, Solicitation 36C26127Q0047.

This walkthrough is for federal contractors who already know how to bid. It explains the job first: three buildings, 98, 209 and 949, about 43,000 square feet of flooring, stair treads, wall base, demolition, asbestos testing and abatement, and new LVT, carpet, resilient stair treads, and wall base. The anticipated quote due date is November 17, 2026, at 3:00 p.m. Pacific. The magnitude is $1M-$2M, the award is price only, and this is a total SDVOSB set-aside.

The thing to pay attention to is a conflict on the face of the bid documents. SOW sections 1.2 and 1.3 require work in buildings 98, 209 and 949, including asbestos abatement. The PCRA and the ILSM cover only 209 and 949, carpet only, and answer the asbestos disturbance question "No." Specification 02 82 11 and 02 82 13.19 contain no ACM quantities, and the only ACM documentation in the package is for Building 209. The drawings do include Building 98, so there is no missing-building gap.

The play is a written question to the contracting officer before the November 3, 2026, 12:00 p.m. Pacific deadline. A pre-bid answer is normally issued to all bidders by amendment, so it buys clarity and a documented position, not a pricing edge over other bidders. The video shows the SOW, PCRA, ILSM, specifications, the solicitation's own attachment lists, the change and differing-site-conditions clauses, and the solicitation's own question instructions.

This is not legal advice. I am not an attorney. This is one person's perspective.
Replace Flooring at VA McClellan: The Asbestos Scope Gap in Solicitation 36C26127Q0047What If Your SAM Registration Gets Denied? (GCExperts Workshop)He Doubled the Lowest Bid — and the Government Gave Him the JobLLC or S Corp? The Government Only Cares About One Thing (GCExperts Workshop)The Sewage Pump Warranty Fight and the Muffin MonsterRFQs and the Bid Tracker: A Federal Contracting StoryWe Sold $100,000 in Tickets to a Workshop That Didnt ExistHe Sold It to the Government for $118,950 — Then Bought It for $51,000The Federal Contractor Journey — Episode 2: The Water Tower That Ate Two YearsA Million Dollars in Debt, Facing Bankruptcy - He Wrote a $10,000 Check AnywayDont Tell Me You Sold the Contract. — Absolutely I Did.Stop Paying for a Contractor’s License — The Feds Only Care About ONE Thing
Sean Reitmeyer | GCExperts |

Replace Flooring at VA McClellan: The Asbestos Scope Gap in Solicitation 36C26127Q0047

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER