Uploaded October 2026 | Updated November 2026, 3 days ago
The Federal Contractor Journey, hosted by Sean Reitmeyer — federal contracting taught by contractors: awards, bids, claims, protests, and the plan-and-spec work that starts it all.
Episode 2: The Water Tower That Ate Two Years — one real job end to end: a Langley Air Force Base water tower the government stopped, then kept stopping, and the daily number that kept a small contractor alive.
Sean Reitmeyer walks through the job from start to finish: the contract was awarded in September 2003 at $1,327,000 with a 266-day performance period. A suspension of work in February 2004 and a differing site condition at the center pier pushed the finish to October 31, 2006, 862 days after the original June 21, 2004 completion date. The episode covers the agreed extended-overhead rate of $661.97 a day and the 331 days left unpaid after the government's payments.
The back half covers this week's federal construction awards and one bid protest decision.
Listen on Apple Podcasts: podcasts.apple.com/us/podcast/the-federal-contractor-journey/id6820943982
Listen on Spotify: open.spotify.com/show/58zIxgtO4JRKEDIl85BVAc
Watch and subscribe on the show's own channel: youtube.com/@federalcontractorjourney
Subscribe to the feed: podcast.gcexperts.com/feed.xml
Presented by GCExperts — gcexperts.com
Disclosure: this episode was produced with synthetic (AI) voice technology. The narration is an AI reproduction of the voice of Sean Reitmeyer.
The Federal Contractor Journey, hosted by Sean Reitmeyer — federal contracting taught by contractors: awards, bids, claims, protests, and the plan-and-spec work that starts it all.
Episode 2: The Water Tower That Ate Two Years — one real job end to end: a Langley Air Force Base water tower the government stopped, then kept stopping, and the daily number that kept a small contractor alive.
Sean Reitmeyer walks through the job from start to finish: the contract was awarded in September 2003 at $1,327,000 with a 266-day performance period. A suspension of work in February 2004 and a differing site condition at the center pier pushed the finish to October 31, 2006, 862 days after the original June 21, 2004 completion date. The episode covers the agreed extended-overhead rate of $661.97 a day and the 331 days left unpaid after the government's payments.
The back half covers this week's federal construction awards and one bid protest decision.
Listen on Apple Podcasts: podcasts.apple.com/us/podcast/the-federal-contractor-journey/id6820943982
Listen on Spotify: open.spotify.com/show/58zIxgtO4JRKEDIl85BVAc
Watch and subscribe on the show's own channel: youtube.com/@federalcontractorjourney
Subscribe to the feed: podcast.gcexperts.com/feed.xml
Presented by GCExperts — gcexperts.com
Disclosure: this episode was produced with synthetic (AI) voice technology. The narration is an AI reproduction of the voice of Sean Reitmeyer.