ITER will rely on 24 electron cyclotorn gyrotrons, each delivering a beam of 1 MW, which is 1000 times more powerful than the one produced by domestic microwaves.
Russia and Japan will manufacture eight each, India will deliver two, and Europe is responsible for six.
To provide Europe's six electron cyclotorn gyrotrons, Fusion for Energy (F4E) has signed a contract with Thales.
In parallel, the Divertor Tokamak Test (DTT), another fusion project based in Italy, has also signed a contract with Thales for the fabrication of 16 gyrotrons.
Read more
Fusion for Energy https://fusionforenergy.europa.eu/
ITER iter.org
DTT https://www.dtt-project.it/index.php
Thales: thalesgroup.com/en
ITER Electron Cyclotron GyrotronsManufacturing the ITER Toroidal Field CoilsPF Coils building July 2011F4E Work progress, Tokamak building complex: February 2011FUSION FOR ENERGY and AIR LIQUIDE - Working together for ITERITER Vacuum Vessel sector 4 completedF4E Work progress, PF Coils building: February 2011Hot forming the ITER vacuum vesselITER Tokamak complex March 2012Massive ITER Magnet ready!Tokamak complex November 2011ITER Worksite - F4E - 2015 Milestones / Etapes importantes du chantier ITER 2015
FUSION FOR ENERGY |

ITER Electron Cyclotron Gyrotrons

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER