In our latest project update, our Chief Executive, Mark Wild, visits the EKFB section of the route.

He sees how better preparation, clearer plans and revised contract incentives are helping our teams. They are working more productively, controlling spending and building safely to the right quality.

By late September, we'd moved more than 13 million cubic metres of earth. That's about 40% ahead of plan for this point in the year, and already more than our original target for the whole year.

Also in this video:
• How better preparation and clearer plans are changing the way we work on site
• Our tunnelling towards Euston
• The completed high-speed platforms at Old Oak Common station in west London
• Major viaduct and bridge works in the West Midlands
• How we're preparing to install, test and commission the railway systems

Mark also explains how we're working towards a new integrated plan for the whole project.

There's still plenty to do. We're keeping safety first, spending public money carefully and listening to the communities we work alongside.

📢 Subscribe for the latest news and updates from our high-speed railway, HS2.

00:00 – Opening: evidence of the reset working
01:29 – Progress: major civils moving towards completion
03:09 – Safety and our responsibilities
03:35 – The reset: establishing the foundations for delivery
04:33 – Closing: judge us by delivery

#HS2 #HighSpeedRail #BritishRail #Infrastructure #Jobs #Skills #Growth #BuildingBritain
HS2 Project Update, October 2026HS2 progress in North Buckinghamshire | Turweston to GreatworthHow are HS2 London tunnel segments made? #shortsInside Booth Industries factory | HS2 tunnel cross-passage doors begin to be installedHS2 completes UK’s heaviest bridge slide #shortHS2s Copthall Green Tunnel is complete — Full story in 48 hours #shortIn depth look at HS2’s completed A452 Kenilworth Road BridgeHS2s summer of motorway works: full footage coming soon #shortWe’ve moved a 55-metre span of a bridge over a live railway #ShortsSix months on since historic breakthroughs for HS2’s longest tunnelInside London’s deepest HS2 tunnel: 34 hidden passages revealedGiant steel beams lifted into place under the A43 near Brackley #short
HS2 Ltd |

HS2 Project Update, October 2026

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER