Uploaded October 2026 | Updated November 2026, 3 hours ago
In our latest project update, our Chief Executive, Mark Wild, visits the EKFB section of the route.
He sees how better preparation, clearer plans and revised contract incentives are helping our teams. They are working more productively, controlling spending and building safely to the right quality.
By late September, we'd moved more than 13 million cubic metres of earth. That's about 40% ahead of plan for this point in the year, and already more than our original target for the whole year.
Also in this video:
• How better preparation and clearer plans are changing the way we work on site
• Our tunnelling towards Euston
• The completed high-speed platforms at Old Oak Common station in west London
• Major viaduct and bridge works in the West Midlands
• How we're preparing to install, test and commission the railway systems
Mark also explains how we're working towards a new integrated plan for the whole project.
There's still plenty to do. We're keeping safety first, spending public money carefully and listening to the communities we work alongside.
📢 Subscribe for the latest news and updates from our high-speed railway, HS2.
00:00 – Opening: evidence of the reset working
01:29 – Progress: major civils moving towards completion
03:09 – Safety and our responsibilities
03:35 – The reset: establishing the foundations for delivery
04:33 – Closing: judge us by delivery
#HS2 #HighSpeedRail #BritishRail #Infrastructure #Jobs #Skills #Growth #BuildingBritain
In our latest project update, our Chief Executive, Mark Wild, visits the EKFB section of the route.
He sees how better preparation, clearer plans and revised contract incentives are helping our teams. They are working more productively, controlling spending and building safely to the right quality.
By late September, we'd moved more than 13 million cubic metres of earth. That's about 40% ahead of plan for this point in the year, and already more than our original target for the whole year.
Also in this video:
• How better preparation and clearer plans are changing the way we work on site
• Our tunnelling towards Euston
• The completed high-speed platforms at Old Oak Common station in west London
• Major viaduct and bridge works in the West Midlands
• How we're preparing to install, test and commission the railway systems
Mark also explains how we're working towards a new integrated plan for the whole project.
There's still plenty to do. We're keeping safety first, spending public money carefully and listening to the communities we work alongside.
📢 Subscribe for the latest news and updates from our high-speed railway, HS2.
00:00 – Opening: evidence of the reset working
01:29 – Progress: major civils moving towards completion
03:09 – Safety and our responsibilities
03:35 – The reset: establishing the foundations for delivery
04:33 – Closing: judge us by delivery