The Domestic Terminal Car Park Expansion Project is rapidly progressing, with the structure rising quickly. With more than 1,700 new parking bays on the way, it's hard to miss!
Over 36 concrete pours are planned for the build, with the team currently working on Level 6 with the roof deck now being poured. The suspended structure is rising with precision—each concrete table was built offsite and matched together like Lego to form the superstructure.
The project is due for completion in late 2025 and once finished, will significantly increase car parking capacity within the Domestic Terminal Precinct and improve access for travellers and staff alike. Learn more here: https://www.bne.com.au/corporate/projects/future-bne-projects/domestic-terminal-precinct/p2-parking-extension
The Domestic Terminal Car Park Expansion Project is rapidly progressing, with the structure rising quickly. With more than 1,700 new parking bays on the way, it's hard to miss!
Over 36 concrete pours are planned for the build, with the team currently working on Level 6 with the roof deck now being poured. The suspended structure is rising with precision—each concrete table was built offsite and matched together like Lego to form the superstructure.
The project is due for completion in late 2025 and once finished, will significantly increase car parking capacity within the Domestic Terminal Precinct and improve access for travellers and staff alike. Learn more here: https://www.bne.com.au/corporate/projects/future-bne-projects/domestic-terminal-precinct/p2-parking-extension