This new video shows recent images of HART’s construction along the rail alignment starting from Joint Base Pearl Harbor-Hickam Station to the location of the future Civic Center Station and highlights ongoing work in Segments 2 and 3.

SEGMENT 2 (Joint Base Pearl Harbor-Hickam to Middle Street Transit Center)
• Four (4) stations between Aloha Stadium and the Middle Street Transit Center expected to be completed in the first quarter of 2024.
• Track and Guidway construction work is complete.
• HART has begun core systems installation of power cables, communications systems, and signaling equipment.
• Anticipated transfer to DTS in 2025 for the opening of service.

SEGMENT 3 (Kalihi to Civic Center)
• City Center Utilities Relocation is ongoing. This relocation work will clear the way for future construction of the columns, guideway and stations.
• Downtown Utilities Relocation work is expected to be complete in the fourth quarter of 2024.
• Dillingham Utilities Relocation work is expected to be complete in the first quarter of 2026.


#hnlrail #followHART #railupdate #hitachirail

Music by Stockaudios from Pixabay
Construction Update  // January 2024Construction Update  // August 2024Board of Directors: Project Oversight, Finance, HR, GALM Committee | 3-20-2026Board of Directors Meeting  |  Project Oversight Committee  |  August 19, 2021Rail Construction Traffic Update in 60 Seconds - Pedestrian Bridge Installation on Kamehameha HwySpecial Board Meeting and Board Of Directors Meeting  |  April 21, 2022 & April 22, 2022HART Board of Directors Meeting and Internal Audit Committee Meeting  |  March 16, 2023Construction Progress // April 2021Construction in Progress // June 2021Construction Update // Makalapa to Lelepaua // Drone Flyover // June 2025Board of Directors, Project Oversight & GALM Committee Meeting  |  August 22, 2025Construction Update // Kualaka‘I to Honouliuli Station // Drone Flyover // January 2022
Honolulu Rail Transit |

Construction Update // January 2024

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER