🚆✨ View our latest video of HART’s construction progress from Aloha Stadium Station to the location of the future Civic Center Station. The video highlights ongoing work in Segments 2 and 3.

SEGMENT 2
- Construction completion: Expected to be substantially complete in Fall 2024.
- Core Systems: 95% complete
- Third Rail Energization: Began in June 2024; vehicle testing underway
- Operational Readiness: Transfer of assets to the City Department of Transportation Services targeted for late 2025

SEGMENT 3 | CITY CENTER SEGMENT
- Downtown/Iwilei and Kakaako Utilities Relocation: Completion expected in Q4 2024; Dillingham Utilities Relocation: Completion expected in Q1 2026
- City Center Guideway and Stations Construction Procurement: Contract award is expected late August 2024

#hnlrail #followHART #railupdate #hitachirail

Music by Oleg Fedak from Pixabay
Construction Update  // August 2024Board of Directors: Project Oversight, Finance, HR, GALM Committee | 3-20-2026Board of Directors Meeting  |  Project Oversight Committee  |  August 19, 2021Rail Construction Traffic Update in 60 Seconds - Pedestrian Bridge Installation on Kamehameha HwySpecial Board Meeting and Board Of Directors Meeting  |  April 21, 2022 & April 22, 2022HART Board of Directors Meeting and Internal Audit Committee Meeting  |  March 16, 2023Construction Progress // April 2021Construction in Progress // June 2021Construction Update // Makalapa to Lelepaua // Drone Flyover // June 2025Board of Directors, Project Oversight & GALM Committee Meeting  |  August 22, 2025Construction Update // Kualaka‘I to Honouliuli Station // Drone Flyover // January 2022Segment 2 Highlight  |  Kahauiki to Hālawa  |  Drone Timelapse  |  October 2025
Honolulu Rail Transit |

Construction Update // August 2024

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER