A contractor is excavating an urban infill site for the development of a new high-rise building. During excavation, the contractor uncovers a pile of buried debris that appears to be asbestos containing materials from a previous demolition. Phase I and Phase II reports conducted for the site do not indicate the presence of any hazardous materials. The contractor stops the work and, after discussing with the owner and an experienced abatement contractor, determines that it will cost $20,000 to remove the material and the removal will be complete within 5 days. Which of the following is an appropriate course of action for the architect to take?

A. Redesign the foundation so the hazardous material can be encapsulated in place.
B. Issue a minor change in the work for the contractor to remove the material.
C. Request that the owner hire a separate abatement contractor to remove the material.
D. Issue a change order for $20,000 and an extension of 5 days.

đź’ˇAnswer: D
CE Practice Exam Question #shorts #architecturePPD Practice Exam Question #shortsPractice Management Mock Exam Question #4 | ARE 5.0 PcM Mock Exam #architectureProgramming & Analysis Mock Exam Question #5 | ARE 5.0 PA Mock Exam #architectureGroup Your Exam #shortsARE Live: Construction & Evaluation Mock Exam | ARE 5.0 CE Exam 2024PjM Practice Exam Question #shorts #architectureMock Exam: Roof Cricket #shortsPjM Practice Exam Question #shorts #architecturePA Practice Exam Question #shorts #architectureCE Practice Exam Question #shorts #architectureConstruction & Evaluation Mock Exam Question #4 | ARE 5.0 CE Exam 2024 #architecture
Black Spectacles |

CE Practice Exam Question #shorts #architecture

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER