An architect is working on a project that has experienced several delays:
โ Owner initiated finish change at lobby - 5 days
โ Incorrect installation of guardrails - 3 days
โ Miscoordination of contract documents - 2 days
โ Delay in delivery of pavers - 5 days
The owner and contractor have agreed to liquidated damages in the amount of $5,000 for each day that the project is delayed beyond the substantial completion date. What is the total amount of liquidated damages that the contractor should expect to pay?
A. $75,000
B. $40,000
C. $50,000
D. $0
๐กAnswer: B
An architect is working on a project that has experienced several delays:
โ Owner initiated finish change at lobby - 5 days
โ Incorrect installation of guardrails - 3 days
โ Miscoordination of contract documents - 2 days
โ Delay in delivery of pavers - 5 days
The owner and contractor have agreed to liquidated damages in the amount of $5,000 for each day that the project is delayed beyond the substantial completion date. What is the total amount of liquidated damages that the contractor should expect to pay?
A. $75,000
B. $40,000
C. $50,000
D. $0
๐กAnswer: B