Uploaded December 2023 | Updated September 2026, 1 week ago
The Camms Road, Cranbourne level crossing is no more β marking our 73rd removal! π₯³
Crews worked 24/7 for 43 days to complete the new road bridge, during this time they:
π§ removed the booms gates
π lifted 22 bridge beams into place
π started building the new Fairfield Street connection
π poured the bridge deck
π¨ finished installing and painting 490 retaining wall panels.
Works will continue in 2024 to complete the new Cranbourne Station plaza, landscaping and building 400 new and upgraded car parks.
The Camms Road, Cranbourne level crossing is no more β marking our 73rd removal! π₯³
Crews worked 24/7 for 43 days to complete the new road bridge, during this time they:
π§ removed the booms gates
π lifted 22 bridge beams into place
π started building the new Fairfield Street connection
π poured the bridge deck
π¨ finished installing and painting 490 retaining wall panels.
Works will continue in 2024 to complete the new Cranbourne Station plaza, landscaping and building 400 new and upgraded car parks.