Uploaded August 2023 | Updated September 2026, 3 weeks ago
Welcome to our Cavite Laguna Expressway subsection 4 – update for the month of August 2023. Malapit na tayo sa exciting part!
Documentation date: August 1 to 18, 2023
The entire subsection 4 which is 3.88 km from Silang East Interchange to Silang Aguinaldo interchange is 91% complete. A few miscellaneous works remain while what remains are the works near WB 15 by dmci and Silang – Aguinaldo Interchange by Leighton.
In this video we will be sharing to you the remaining various PCCP works of the contractors.
Fingers crossed the contractors will meet the deadline for September completion. We have come a long way in observing the works on the CALAX subsection 4.
#CALAX #CaviteLagunaExpressway #MPTSouth
Welcome to our Cavite Laguna Expressway subsection 4 – update for the month of August 2023. Malapit na tayo sa exciting part!
Documentation date: August 1 to 18, 2023
The entire subsection 4 which is 3.88 km from Silang East Interchange to Silang Aguinaldo interchange is 91% complete. A few miscellaneous works remain while what remains are the works near WB 15 by dmci and Silang – Aguinaldo Interchange by Leighton.
In this video we will be sharing to you the remaining various PCCP works of the contractors.
Fingers crossed the contractors will meet the deadline for September completion. We have come a long way in observing the works on the CALAX subsection 4.