During the week of May 12-16, 2025, crews resumed placing the remaining 112 girders at the Hanford Viaduct in Kings County. The remaining girders are being placed near and across the San Joaquin Valley Railroad, bringing these two segments of the viaduct together. This is no easy task as some of these girders can be up to 10-feet tall and weigh between 95-100,000 lbs. A total of 978 pre-cast girders are needed for the Hanford Viaduct and were all manufactured by contractor Dragados-Flatiron Joint Venture.
UPDATE: Hanford Viaduct, Kings CountyCelebrating Caltrain Electrification, an early California High-Speed Rail InvestmentCreating Tracks to Opportunities at High-Speed Rail Networking SummitSpring 2026 California High-Speed Rail Progress ReportLakeland Road Aerial StructureHSRs First Ever Exhibit at the 2024 California State FairARTIC Station and Douglass Road ImprovementsHigh-Speed Rail Media Day at the 2024 California State FairSR 43 Tied Arch Bridge - January 30, 2024Ventura Street Underpass - January 30, 2024Virtual Pre-Bid: RFQ for Environmental & Prelim. Eng. Services for the Heavy Maintenance FacilityRoad 26 Grade Separation - April 12, 2024
California High-Speed Rail Authority |

UPDATE: Hanford Viaduct, Kings County

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER