In this video we rip out the old walkway and driveway and replace it with a walkway/steps and paved driveway. The total time for this project from start to finish was 8 weeks.
Once the old driveway was removed and the 3/4 gravel was down and compacted they recommended waiting 6 weeks for everything to settle and compact fully.
After the asphalt was laid we were told to not drive on it for 2 weeks.
Costs:
Steps $750
Walkway and garden curbing $1850
Driveway removal and re-paving $2400
Total Cost $5000 Canadian $$
0:00 Clips of the process
0:28 Remove old Interlock
1:24 Remove old Driveway
3:18 Dumping A Gravel
4:29 Compact driveway
5:01 Remove grass
6:20 A Gravel Walkway
7:01 Fabric and A gravel
7:21 Installing New steps
9:00 Install interlock
10:54 Polymeric sand
12:32 Pave new driveway
15:%5 Finished driveway
In this video we rip out the old walkway and driveway and replace it with a walkway/steps and paved driveway. The total time for this project from start to finish was 8 weeks.
Once the old driveway was removed and the 3/4 gravel was down and compacted they recommended waiting 6 weeks for everything to settle and compact fully.
After the asphalt was laid we were told to not drive on it for 2 weeks.
Costs:
Steps $750
Walkway and garden curbing $1850
Driveway removal and re-paving $2400
Total Cost $5000 Canadian $$
0:00 Clips of the process
0:28 Remove old Interlock
1:24 Remove old Driveway
3:18 Dumping A Gravel
4:29 Compact driveway
5:01 Remove grass
6:20 A Gravel Walkway
7:01 Fabric and A gravel
7:21 Installing New steps
9:00 Install interlock
10:54 Polymeric sand
12:32 Pave new driveway
15:%5 Finished driveway