Uploaded February 2023 | Updated November 2026, 2 hours ago
Feeling pretty unwell today, coming down with a cold or flu I think!
Tried to rake the area under the building clean, moved the big lumps of concrete and rocks, but the ground was frozen enough to make that a challenge. Beat up big stuff with the digging bar but eventually gave up in favour of getting going on framing.
Installing the insulation retainer batons on the underside of the joists was particularly annoying and consumed much time and profanity. It was easier to do as you went with the joists which was only possible on the southern span as the northern one was already completed when I went to fetch the furring strips.
Finally moved the concrete mixer, hopefully we won't need that for a while.
Ran out of light with only 4 joists to go which was disappointing. Tomorrow I finish the last four joists, close up the east the rim joist and add corner brackets to stiffen the frame a little bit (it is already quite firm), then add the blocking for the ridge beam post landing spots onto the middle girder plus the edges of the floor decking. Then there is a lot of joist to girder ties after square checking followed by insulation cutting and placement before decking can happen.
Feeling pretty unwell today, coming down with a cold or flu I think!
Tried to rake the area under the building clean, moved the big lumps of concrete and rocks, but the ground was frozen enough to make that a challenge. Beat up big stuff with the digging bar but eventually gave up in favour of getting going on framing.
Installing the insulation retainer batons on the underside of the joists was particularly annoying and consumed much time and profanity. It was easier to do as you went with the joists which was only possible on the southern span as the northern one was already completed when I went to fetch the furring strips.
Finally moved the concrete mixer, hopefully we won't need that for a while.
Ran out of light with only 4 joists to go which was disappointing. Tomorrow I finish the last four joists, close up the east the rim joist and add corner brackets to stiffen the frame a little bit (it is already quite firm), then add the blocking for the ridge beam post landing spots onto the middle girder plus the edges of the floor decking. Then there is a lot of joist to girder ties after square checking followed by insulation cutting and placement before decking can happen.