Installation of granite curb continuing down the street with placement of processed aggregate base for the future bike lane and sidewalk bumpouts. Adjustment of utility covers to match the new grades, and connection of the bioswale overflow structure into the existing catch basin.
State Street Project - Construction Update 3New Haven Peanut Roundabout - Construction Update 5Wall St Contraflow Bike Lane CompletionLitchfield, CT Walkabilityeclipse i hardly knew herNew Traffic Signal for Two-Way ConversionIn-Road Crosswalk LightsRight Turn Signal Separation for Trail CrossingManchester, CT Main Street ProjectBikeway Signal Separation in ChicagoEdgewood Ave Cycletrack OverviewNew Haven, CT 2011 - 2022 pt.1