San Onofre Nuclear Power Plant Offline until 2013 says NRC
Gary Headrick questions the NRC in Dana Point Oct 9, 2012
youtube.com/watch?v=REdPu2TaodQ
Published on Oct 22, 2012 by Ace Hoffman

Recorded at a Nuclear Regulatory Commission Public Meeting October 9th, 2012

Note #1: Mode 3 testing was begun approximately one week later.

Note #2: The girl in the blue shirt trying to get called on... never was. This happened to a lot of people that night.

Video by Ace Hoffman
acehoffman.org
~~~~~~~~~~~~~~~~~~~~~~~~~~~`

there is a HUGE list of videos to watch about how BAD this situation is! https://www.youtube.com/results?search_query=gundersen+san+onofre&oq=gundersen+san+onofre&gs_l=youtube.12...2610.7316.0.9522.20.19.0.1.1.0.108.1297.18j1.19.0...0.0...1ac.1.5WfCxAqrKH0

Dana Point Meeting Scheduled for Tuesday on San Onofre Nuclear Plant
nbclosangeles.com/news/local/San-Onofre-Nuclear-Power-Plant-Public-Hearing-173329591.html

San Onofre Nuclear Plant Offline Until 2013: NRC
Southern California Edison submitted a plan last week that outlines plans for the shuttered generators
UPDATE HERE: nbclosangeles.com/news/local/san-onofre-nuclear-plant-173394591.html

The San Onofre plant's power generators -- Unit 2 and Unit 3 -- were deactivated in January. Unit 2 was taken off-line for planned maintenance. Unit 3 was shut down after a leak was detected in one of its steam generator tubes.

Last week, Southern California Edison, which runs the Northern San Diego County plant and co-owns it with San Diego Gas & Electric and the city of Riverside, submitted a plan to the NRC that outlines how it will restart Unit 2. The generator would be restarted at 70 percent power for a trial period of five months.

More inspections would follow.
READ THIS DOCUMENT: songscommunity.com/docs/cal/CoverLetter.pdf
Southern California Edison submitted a plan last week that outlines plans for the shuttered generators

NRC officials have said the agency has "several months" of work ahead before a decision is reached on the plant's future.

The NRC's regional administrator, San Onofre Chief Nuclear Officer Pete Dietrich, Robert Oglesby and Ed Randolph of the California Public Utilities Commission, and nuclear energy activists are expected to attend the Dana Point meeting.

The panel discussion will be followed by a question-answer session.
San Onofre Nuclear Power Plant Offline until 2013 says NRCFukushima Nuclear Reactor #1 Update 10/10/12Fukushima: The Massive Deception & Cover-up (contd)Fukushima Incredible Update! MORE Active Faults, Residents Return Home WTF 12/14/12Fukushima Meltdown update 10/2/12LOTS of NUCLEAR trouble USA and Japan 6/28/11Obama CAUGHT AGAIN! (attention to details!)Fukushima Unit 3 SFP, More Contamination in Fish & Tokyo: Arnie GundersenLegal Action to Stop Nuclear Power in Japan 8/22/12 Fukushima update!Fukushima Nuclear DISGRACE!SFP#4 Controversy According to NRC FOIA documents (LINK BELOW)Fukushima Wasnt Prepared to Explode & Melt Down (NO SHIT!) update 9/7/12
MsMilkytheclown |

San Onofre Nuclear Power Plant Offline until 2013 says NRC

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER