The Process and Stages a Post-Tension Floor Construction
with can be Devided 17 Steps as follow :

Step 1 Fromwork Setup
Step 2 Fixing Slab Edge Formwork
Step 3 Placing of Bottom Reinforcement
Step 4 Fixing Anchorage Bursting Reinforcemant
Step 5 Placing Post-Tension Tendon
Step 6 Fixing of Barchair for Post-Tension Tendon
Step 7 Placing Anchorage, Pocket Former and Groutvent
Step 8 Placing of Top Reinforcement
Step 9 Concreting of Slab
Step 10 Remove Slab Edge Formwork
Step 11 Remove Pocket Former
Step 12 Placing Anchor Head and Wedge
Step 13 Stressing
Step 14 Cutting End of Strand
Step 15 Capping Stressing Recess with Cement Mortar
Step 16 Grouting
Step 17 Remove Formwork and Shoring 50%

Repeat First Step for Construction of The Next Floor