Uploaded January 2026 | Updated September 2026, 3 weeks ago
Three steel girders were installed on span 7 to 8 this week, These steel girders were imported from Vietnam (Vinh Hung). The girders were placed above Tullahan river. The temporary steel bridge installed along Tullahan river was the launching area of the girder. As for the other parts of section 1A, the first piers installed with girders concrete pouring has began. The ramps along NLEX is also showing progress while you can visibly see now the off and on ramps from the Quezon City side (Just after Tullahan river). More houses are cleared for the alignment.
Congratulations to the contractor for completing the first three steel girder installation.
Three steel girders were installed on span 7 to 8 this week, These steel girders were imported from Vietnam (Vinh Hung). The girders were placed above Tullahan river. The temporary steel bridge installed along Tullahan river was the launching area of the girder. As for the other parts of section 1A, the first piers installed with girders concrete pouring has began. The ramps along NLEX is also showing progress while you can visibly see now the off and on ramps from the Quezon City side (Just after Tullahan river). More houses are cleared for the alignment.
Congratulations to the contractor for completing the first three steel girder installation.



