This is a brief instructional video for how to use the Levy to Move Seattle reporting dashboard. Approved by voters in November 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city. The levy provides roughly 30% of the City's transportation budget and replaces the 9-year, $365 million Bridging the Gap levy approved by voters in 2006.
Transcript: Hi everyone,
Today I am going to review how to use the Levy to Move Seattle reporting dashboard which is hosted through Tableau. This dashboard is updated quarterly as well as annually, so our annual update will occur on March 30 and then we will update the dashboard quarterly on April 30, July 30 and October 30.
The dashboard has a toggle menu at the top that allows you to select the reporting period. Clicking this menu shows you can look at a summary of 2021 data all the way back to 2016 data when we started implementing projects funded by the Levy. We can also look at data from 2016 to present, which is the life of the Levy. We’ll start by looking at just 2021 data as an example.
Let’s click 2021 summary.
On the left you’ll see three tabs, Safe Routes, Maintenance and Repair and Congestion Relief, three categories of Levy programs. There are 30 programs total.
We will start by looking at Safe Routes.
Each program has an ID. For example, Levy program 2 is Dafe Routes to School.
On the home page, you can see how many projects were completed in each quarter of 2021.
You will also see on the left that we planned to complete nine and we ultimately completed 22 in 2021.
That brings us to the key at the top left. If the program is accompanied by two green check marks, we exceeded our planned accomplishment; if one check mark, we met our planned accomplishment; if a little red flag, we met 75-99% of the planned accomplishment. A red exclamation point means that we met less than 75% of the planned accomplishment.
You’ll see an example in program 1, Vision Zero Corridors. We planned 3, but completed two, so that has a red exclamation point next to it.
This is a brief instructional video for how to use the Levy to Move Seattle reporting dashboard. Approved by voters in November 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city. The levy provides roughly 30% of the City's transportation budget and replaces the 9-year, $365 million Bridging the Gap levy approved by voters in 2006.
Transcript: Hi everyone,
Today I am going to review how to use the Levy to Move Seattle reporting dashboard which is hosted through Tableau. This dashboard is updated quarterly as well as annually, so our annual update will occur on March 30 and then we will update the dashboard quarterly on April 30, July 30 and October 30.
The dashboard has a toggle menu at the top that allows you to select the reporting period. Clicking this menu shows you can look at a summary of 2021 data all the way back to 2016 data when we started implementing projects funded by the Levy. We can also look at data from 2016 to present, which is the life of the Levy. We’ll start by looking at just 2021 data as an example.
Let’s click 2021 summary.
On the left you’ll see three tabs, Safe Routes, Maintenance and Repair and Congestion Relief, three categories of Levy programs. There are 30 programs total.
We will start by looking at Safe Routes.
Each program has an ID. For example, Levy program 2 is Dafe Routes to School.
On the home page, you can see how many projects were completed in each quarter of 2021.
You will also see on the left that we planned to complete nine and we ultimately completed 22 in 2021.
That brings us to the key at the top left. If the program is accompanied by two green check marks, we exceeded our planned accomplishment; if one check mark, we met our planned accomplishment; if a little red flag, we met 75-99% of the planned accomplishment. A red exclamation point means that we met less than 75% of the planned accomplishment.
You’ll see an example in program 1, Vision Zero Corridors. We planned 3, but completed two, so that has a red exclamation point next to it.