A major milestone is complete on the Downtown Rail Reconstruction Project! 🚊✨
RTD has officially wrapped up its 86-day reconstruction of the light rail crossing at Kalamath Street and Colfax Avenue right on schedule.

Here’s what crews accomplished:
πŸ”§ Rebuilt the entire crossing from the ground up
πŸš‰ Replaced 1,300 feet of track
πŸ”€ Installed 1,100 feet of special trackwork
πŸš— Reconstructed one vehicle crossing
πŸšΆβ€β™€οΈ Upgraded two pedestrian crossings
πŸ’Ό Advanced a key piece of RTD’s $152 million investment to modernize aging track and deliver a smoother, more reliable ride

This work sets the stage for what’s next:
πŸ› οΈ Reconstruction along Colfax Avenue (beginning 2026)
πŸ”„ Additional Downtown Loop track replacements
πŸ“ Continued design work along Welton Street
RTD will keep sharing updates as the next phases take shape.

Stay tuned and follow the progress at rtd-denver.com/railproject.
#DowntownRailReconstruction
Downtown Rail Reconstruction: Kalamath CompleteJoin Us for Winter Bike to Work Day 2026Ask An Operator: What’s the first thing customers notice?2026 TAG Awardee WebinarBuilding a Better RTDTake RTD to Noah Kahan at Coors FieldSafety with Maria - Stay Behind The Yellow LineSafety With Maria- 4th of JulyEnjoy Zero Fare for Youth This Spring BreakOur Transit Green Flags
Regional Transportation District |

Downtown Rail Reconstruction: Kalamath Complete

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER