CSX | Fitzgerald Mega Block @CSXOfficial
CSX | Fitzgerald Mega Block  @CSXOfficial
Uploaded June 2026 | Updated September 2026, 3 weeks ago
CSX engineering crews recently completed a 10-week mega block on our Fitzgerald Subdivision ahead of schedule, safely delivering major infrastructure improvements along a key north-south route. Working overnight to minimize disruption, employees installed 95,000 ties, replaced 1,500 switch ties, upgraded curves, and completed track surfacing to strengthen reliability across the corridor. This is what commitment to a safer, more reliable railroad looks like.