Construction Update // May 2025 @HonoluluRailTransit
Construction Update // May 2025  @HonoluluRailTransit
Uploaded May 2025 | Updated November 2026, 3 hours ago
Check out our latest video for a behind-the-scenes look at the progress on Honolulu’s rail system 🚆✨

SEGMENT 2 Airport Guideway & Stations ✈️
• Trial Runs begin July 2025 with 26 test case scenarios
• System Demonstration starts September 2025 – aiming for 98.5% availability over 30 days: Riders will deboard at Aloha Stadium during testing
• Once safety & performance standards are met, assets will transfer to DTS
• Anticipated date for transfer to DTS: October 2025

SEGMENT 3 - City Center Section 🌃
• Guideway column construction begins Summer 2025. Geotechnical boring began January 2025
• Downtown utility relocations – Completion by Q2 2025
• Dillingham utility relocations – Completion by Q1 2026

#hnlrail #followHART #railupdate #hitachirail

Music by AudioCoffee from Pixabay
Construction Update // May 2025HART Board of Directors and Project Oversight Committee Meeting | January 20, 2023Rail Construction Traffic Update in 60 Seconds - Kamehameha Highway Left Turn/U-Turn Lane ClosureConstruction Update // Āhua to Kahauiki Station // Drone Flyover // September 2024Project Oversight, Finance, and Human Resources Committee Meeting  |  April 12, 2024HART Committee - Government Affairs, Audit, Legal Matters, Project Oversight — February 11, 2021Construction Update // City Center Utilities Relocation // Drone Flyover // February 2025Board of Directors, Project Oversight, Finance Committee Meeting | December 20, 2024HART Board of Directors Meeting  |  April 27, 2023HART Board of Directors Meeting  |  January 19, 2024Construction Update // Hālawa to Lelepaua Station // Drone Flyover // July 2024HART Board of Directors Meeting   |  August 23, 2024