Happy #AlohaFriday! 🌈 🌺 🤙
🚆✨ Check out our latest video to see HART's construction progress and ongoing work in Segments 2 and 3! Here's a brief status update:
Segment 2 //
Construction of the guideway and stations is ongoing, with substantial completion by Summer 2024. Core System installation is in progress, and transfer to the Department of Transportation Services for passenger operations is anticipated in late 2025.
Segment 3 //
Ongoing utilities relocation in Downtown and Dillingham, with Downtown/Iwilei and Kakaako completing in Q4 2024 and Dillingham in Q1 2026. Procurement for the City Center Guideway and Stations construction is underway, with contract award expected in late 2024.
#hnlrail #followHART #railupdate #hitachirail
Music by AudioCoffee from Pixabay
Happy #AlohaFriday! 🌈 🌺 🤙
🚆✨ Check out our latest video to see HART's construction progress and ongoing work in Segments 2 and 3! Here's a brief status update:
Segment 2 //
Construction of the guideway and stations is ongoing, with substantial completion by Summer 2024. Core System installation is in progress, and transfer to the Department of Transportation Services for passenger operations is anticipated in late 2025.
Segment 3 //
Ongoing utilities relocation in Downtown and Dillingham, with Downtown/Iwilei and Kakaako completing in Q4 2024 and Dillingham in Q1 2026. Procurement for the City Center Guideway and Stations construction is underway, with contract award expected in late 2024.
#hnlrail #followHART #railupdate #hitachirail
Music by AudioCoffee from Pixabay