Construction Update  // January 2025 @HonoluluRailTransit
Construction Update  // January 2025  @HonoluluRailTransit
Uploaded January 2025 | Updated November 2026, 6 hours ago
Check out this video for HART’s construction progress and ongoing work!
🚆✨

SEGMENT 2 (Airport Guideway & Stations):
• Stations set for Q2 2025 completion
• Core Systems are nearly complete
• Train testing underway, transfer to DTS in late 2025

SEGMENT 3 (City Center):
• Utilities relocation ongoing: Downtown - Completion expected in Q2 2025;
Dillingham - Completion expected in Q1 2026
• City Center construction contract was awarded to Tutor Perini Corporation. Construction is anticipated to begin in the summer of 2025.

#hnlrail #followHART #railupdate #hitachirail

Music by Mykola Sosin from Pixabay
Construction Update  // January 2025Construction Update  // August 2022Special BOD Meeting, Project Oversight, Human Resources Committee Meeting  |  March 10, 2022HART Finance, HR and BOD Meetings   January 21, 2021Construction Update // Āhua to Kahauiki Station // Drone Flyover // July 2023Construction Update  // September 2023Construction Update // Pouhala to Waiawa Station // Drone Flyover // March 2022HART Special Board of Directors Meeting |  June 6, 2025Board of Directors Meeting  |  September 21, 2021Construction Update // Āhua to Kahauiki Station // Drone Flyover // November 2021HART Historic Preservation Workshop  |  Don Hibbard  |  August 9, 2025Trial Running highlight // Hō‘ae‘ae Station  // Drone Flyover // March 2023
Honolulu Rail Transit |

Construction Update // January 2025

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER