At a recent site visit, the architect notices that blocking hasn’t been installed in the wall for future grab bars at several bathrooms in a new multifamily residential building. The contractor states that they installed blocking where it’s called for on the interior elevations, but the architect notes that they also provided standard blocking details that apply to all bathrooms. The contractor disagrees, and states that adding the blocking will delay the project because sheetrock installation is scheduled to begin tomorrow. How should the project team remedy the situation?
A. Proceed without blocking in certain bathrooms
B. Issue a change order for additional time to allow for blocking to be installed
C. Install the blocking and adjust the sheetrock installation schedule accordingly
D. Install blocking after the sheetrock is installed to maintain the schedule
💡Answer: C
At a recent site visit, the architect notices that blocking hasn’t been installed in the wall for future grab bars at several bathrooms in a new multifamily residential building. The contractor states that they installed blocking where it’s called for on the interior elevations, but the architect notes that they also provided standard blocking details that apply to all bathrooms. The contractor disagrees, and states that adding the blocking will delay the project because sheetrock installation is scheduled to begin tomorrow. How should the project team remedy the situation?
A. Proceed without blocking in certain bathrooms
B. Issue a change order for additional time to allow for blocking to be installed
C. Install the blocking and adjust the sheetrock installation schedule accordingly
D. Install blocking after the sheetrock is installed to maintain the schedule
💡Answer: C