Boston Lodge Switch Room rebuild

At the end of November, the volunteer Electrical Gang held a four-day working party to renew all of the electrical switchgear for Boston Lodge.

This process had been planned for many months and involved a total shutdown of power to Boston Lodge.

The old switchgear was removed and brand new hardware installed, connected up and tested.

With the exception of the final testing and sign-off, all work was done by volunteers.

This weekend alone, the Electrical Gang saved the railway many tens of thousands of pounds and their dedication meant that disruption to the site was limited to only two work-days.

This was a huge achievement and just shows what can be done by our amazing volunteers.

To find out more about joining the Electrical Team or any other volunteering activity, please email: volunteer@ffwhr.com



Ailadeiladu Ystafell Switsh Boston Lodge

Ar ddiwedd mis Tachwedd, cynhaliodd ‘Gang’ gwirfoddolwyr Electronic sesiwn weithio pedwar diwrnod i adnewyddu'r holl offer switsh trydanol ar gyfer Boston Lodge.

Roedd y broses hon wedi'i chynllunio ers misoedd lawer ac roedd yn cynnwys cau pŵer i Boston Lodge yn llwyr.

Tynnwyd yr hen offer switsio a gosodwyd caledwedd newydd sbon, ei gysylltu a'i brofi.

Heblaw profion terfynol a'r gwaith cymeradwyo, gwirfoddolwyr oedd yn gwneud yr holl waith.

Y penwythnos hwn yn unig, arbedodd y ‘Gang’ Electronic ddegau o filoedd o bunnoedd i'r rheilffordd ac roedd eu hymroddiad yn golygu bod tarfu ar y safle wedi'i gyfyngu i ddau ddiwrnod gwaith yn unig.

Roedd hwn yn gyflawniad enfawr ac mae'n dangos yr hyn y gall ein gwirfoddolwyr anhygoel ei gwblhau.

I ddarganfod mwy am ymuno â'r Tîm Trydanol neu unrhyw weithgaredd gwirfoddoli arall, anfonwch e-bost: volunteer@ffwhr.com
Boston Lodge Switch Room rebuildHave A Go: Build A Carriage Workshop.Fairlies of the Ffestiniog - Part Three  How they workLoco Round-UpPlatinum Jubilee Cavalcade Timelapse 22nd June 2025Wickham Trolley - Moving Pictures Special Edition 12/9/25Moving Pictures One Hundred and Two - 23/12/24Mary Ann on the CobThe Snowdonian 2025New Den Work: Prepare for Extension - TimelapseFRS 70th - Michael and SamNG15 Kalahari - Beddgelert to Pont Croesor
Ffestiniog & Welsh Highland Railways |

Boston Lodge Switch Room rebuild

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER