Beavers living in pipe among setbacks delaying Riverside Drive construction @Wcpo9
Beavers living in pipe among setbacks delaying Riverside Drive construction  @Wcpo9
Uploaded November 2026 | Updated November 2026, 1 day ago
Construction at Riverside Drive has been delayed due to weather, conflicts with underground utility lines and the discovery of beavers living in a pipe that was set to be decommissioned, according to the Metropolitan Sewer District (MSD)

Due to these recent setbacks, MSD says construction is now expected to be complete by the end of November. It was originally planned to be wrapped up by the end of October.
Beavers living in pipe among setbacks delaying Riverside Drive constructionNephew Remembers Cecil Collins After Fatal Evanston House FireOhio Rep. Jim Jordan Elected House Republican Minority LeaderBengals head coach Zac Taylor discusses the NFLs international games1 Dead In Overnight Westwood Shooting
WCPO 9 |

Beavers living in pipe among setbacks delaying Riverside Drive construction

SHARE TO X SHARE TO REDDIT SHARE TO FACEBOOK WALLPAPER