The Little Bear Creek Advance Mitigation Site is a six-year project created by Snohomish County to mitigate transportation projects identified in the comprehensive plan. Totaling $4.2 million through 2023, the wetland project acquired land, used non-linear planning, and field-fit designed, and constructed a 17-acre wetland mitigation bank.
With an ongoing maintenance cost of $400,000 over the next 10 years, the project will save $30 million for at least 10 transportation projects already identified in the comprehensive plan.
“We know that combining the mitigation needs for future road projects and mitigation efforts into a single site before it’s needed, we create significant financial savings and a strong ecological impact. This was a bold public works project as very few organizations handle wetland mitigation in this way,” said Snohomish County Public Works Director Kelly Snyder. “In all, creating the mitigation site took seven years, however it benefits the County and the public in perpetuity.”
Check out project details: snohomishcountywa.gov/4032/Advance-Mitigation-Site-at-Little-Bear-C
Learn more about the Governor's Smart Communities Awards: commerce.wa.gov/growth-management/education-outreach/smart-communities
The Little Bear Creek Advance Mitigation Site is a six-year project created by Snohomish County to mitigate transportation projects identified in the comprehensive plan. Totaling $4.2 million through 2023, the wetland project acquired land, used non-linear planning, and field-fit designed, and constructed a 17-acre wetland mitigation bank.
With an ongoing maintenance cost of $400,000 over the next 10 years, the project will save $30 million for at least 10 transportation projects already identified in the comprehensive plan.
“We know that combining the mitigation needs for future road projects and mitigation efforts into a single site before it’s needed, we create significant financial savings and a strong ecological impact. This was a bold public works project as very few organizations handle wetland mitigation in this way,” said Snohomish County Public Works Director Kelly Snyder. “In all, creating the mitigation site took seven years, however it benefits the County and the public in perpetuity.”
Check out project details: snohomishcountywa.gov/4032/Advance-Mitigation-Site-at-Little-Bear-C
Learn more about the Governor's Smart Communities Awards: commerce.wa.gov/growth-management/education-outreach/smart-communities