Create Elements by Intersection - Advanced Computational Design in Dynamo
updated
Join Black Spectacles and architect Garric Baker to learn the best study strategies for passing the CE exam.
On this episode of ARE Live, we walk through a mock exam for the Construction & Evaluation division of the ARE 5.0. You'll learn about the CE exam and we'll cover topics related to project delivery methods and phases, contingency allowance, how to implement FF&E allowance, types of bonds during construction and how to determine ownership of construction documents.
Timestamps:
06:12 - Question No. 1
18:58 - Question No. 2
20:18 - Question No. 3
22:23 - Question No. 4
23:57 - Question No. 5
26:05 - Question No. 6
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
Join Black Spectacles and architect Garric Baker to learn the best study strategies for passing the PPD exam.
On this episode of ARE Live, we walk through a mock exam for the Project Planning & Design division of the ARE 5.0. You'll learn about the PPD exam and we'll cover topics related to advising on historic window replacement options, choosing parking solutions with cost analysis, calculating buildable area considering zoning setbacks, determining stage size and plumbing for a theater, and assessing windows for energy efficiency standards.
Timestamps:
05:51 - Question No. 1
10:24 - Question No. 2
14:25 - Question No. 3
17:12 - Question No. 4
24:11 - Question No. 5
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
On the third episode of Licensure Stories, Marc Teer (founder of Black Spectacles) is joined by Jamie Bieser, an accomplished architect at Widseth based in Baxter, Minnesota.
You’ll learn how Jamie achieved his "unreachable goal" of becoming a licensed architect, how he studied to pass each exam on the first try, and how his career changed once he became a licensed architect. Finally, Jamie wants to remind you to "remember to play" and "stay fascinated"!
Here's how Jamie passed all 6 divisions of the ARE 5.0 Exam: Practice Management, Project Management, Programming & Analysis, Project Planning & Design, Project Development & Documentation and Construction & Evaluation. This is Jamie Bieser's Licensure Story.
Meet Jamie: blog.widseth.com/bieser-becomes-registered-architect
Read more on Licensure Stories: blackspectacles.com/podcast
On the second episode of Licensure Stories, Marc Teer (founder of Black Spectacles) is joined by Jeff Head, an accomplished architect at Pivot North based in Boise, Idaho.
You’ll learn how Jeff studied to pass all 6 exams of the ARE 5.0 in 4 months, what motivated Jeff to get licensed, and how he celebrated once he passed. Here's how Jeff passed all 6 divisions of the ARE 5.0 Exam: Practice Management, Project Management, Programming & Analysis, Project Planning & Design, Project Development & Documentation and Construction & Evaluation. This is Jeff Head's Licensure Story.
Meet Jeff: pivotnorthdesign.com/people/jeff-head
Read more on Licensure Stories: blackspectacles.com/podcast
On this episode of Licensure Stories, Marc Teer (founder of Black Spectacles) is joined by Andres Gonzalez, an accomplished architect at BLUR Workshop based in Atlanta, Georgia.
You’ll learn why Andres chose to get licensed, how Andres studied with English as his second language, how he changed his mindset after failing two exams in a row, and what licensure means to him. Here's how Andres passed all 6 divisions of the ARE 5.0 Exam (Practice Management, Project Management, Programming & Analysis, Project Planning & Design, Project Development & Documentation and Construction & Evaluation). This is Andres Gonzalez’s Licensure Story.
Meet Andres: blurworkshop.com/people#/andres-gonzalez
Read more on Licensure Stories: blackspectacles.com/podcast
Join Black Spectacles and architect Garric Baker to learn the best study strategies for passing the PjM exam.
On this episode of ARE Live, we walk through a mock exam for the Project Management division of the ARE 5.0. You'll learn about the PjM exam and we'll cover topics related to the difference in contract types, an architect's liability for contractor recommendations, responsibility for hazardous conditions and firm billing rate calculations.
Timestamps:
04:53: Question No. 1
11:35: Question No. 2
17:40: Question No. 3
20:36: Question No. 4
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
🔍 Scenario: The developer is considering using the site for a multi-family residential building of type IIIA construction. The building will include laundry facilities, a gym, a lobby with a front desk, and a small coffee shop. The coffee shop will be accessible to the public from Peter Street.
What is the maximum height of this building?
A. 65 feet
B. 75 feet
C. 85 feet
D. 90 feet
🔍 Scenario: The developer is concerned about the ability to develop a parking garage with adequate stall counts and parking flow. They are interested in providing only the minimum required number of spaces and are deciding between a residential building with 40 units or a mall building.
How many more parking spaces will need to be provided for the mall building rather than the residential building? Assume a building area of 40,000 sq. ft.
A. 134 parking spaces
B. 80 parking spaces
C. 54 parking spaces
D. 50 parking spaces
🔍 Scenario: After securing the site, the developer has provided the zoning ordinance and site information to the architect. The developer has asked the architect to provide a feasibility report and include information regarding unique considerations for this site. The developer intends to use this feasibility report to inform the project program, schedule, and budget.
What unique considerations should the architect include in this report? Select the four that apply.
A. Presence of chemical waste
B. Increase in FAR if retail is provided along Peter Street
C. Project must be LEED Silver equivalent
D. Proximity to the coastline
E. Majority office program not permissible
F. Must hold three public comment periods
🔍 Scenario: A developer has just secured a site in downtown Detroit. They have not yet decided how the property will be developed and have asked the architect to provide suggestions.
Based on the exhibits, which of the following project types could be built on this site?
A. Professional workplace
B. Mixed use development
C. Library
D. Single family residential
🔍 Scenario: The architect has been hired to do a site feasibility study for a repeat client. The 40,000 sq. ft rectangular site is located near a lake shoreline. It falls within the city’s low development-zone, thus having an FAR of 1.5 and a 10’ setback on each side. The client wishes to develop the property into multi-family housing.
Which of the following are possible massing configurations for a development on this site? Select the two that apply.
A. 1 story, 40,000 sq. ft floor plate
B. 1 story, 60,000 sq. ft floor plate
C. 2 story, 30,000 sq. ft floor plate
D. 2 story, 40,000 sq. ft floor plate
E. 3 story, 20,000 sq. ft floor plate
F. 3 story, 30,000 sq. ft floor plate
🔍 Scenario: The firm has just hired a mid-level project architect with a $124,800 salary. Assume the following information:
Net multiplier = 3.5
Overhead rate = 1.4
Profit multiplier = 1.1
Utilization rate = 80%
What is an appropriate billable rate for this employee?
A. $220/hour
B. $210/hour
C. $200/hour
D. $190/hour
Join Black Spectacles and architect Marissa Yee to learn the best study strategies for passing the PA exam.
On this episode of ARE Live, we walk through a mock exam for the Programming & Analysis division of the ARE 5.0. You'll learn about the PA exam and we'll cover topics related to assessing site feasibility for multi-family housing, exploring various massing configuration options for development, and understanding feasibility reports with site-specific details.
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
Timestamps:
04:01 Question No. 1
08:03 Question No. 2
13:42 Question No. 3
19:45 Question No. 4
23:59 Question No. 5
We're bringing you a clip from ARE Live featuring a PcM Mock Exam question!
🔍 Scenario: After strategizing goals for the upcoming three-year period, the firm decides that it would like to implement evidence-based design on one project. Which of the following clients and project combination is the most likely application for evidence-based design?
A. Multi-family housing with a cost-conscious developer.
B. A daycare facility with a maximum of 9 students.
C. Restrooms for a local park with the county’s parks and recreation division as the client.
D. A national retailer who plans to open three new locations.
We're bringing you a clip from ARE Live featuring a PcM Mock Exam question!
🔍 Scenario: The firm has recently won a project, a new school building on an existing elementary campus. The architect is looking to establish overall design principles to influence the project’s trajectory. When asked about their thoughts on overall design principles, the client seems uninterested in having a conversation and instead points to the RFP for the stated design principles. The design team has already viewed this document and found it to be vague.
What should the architect recommend?
A. Use the client’s design principles from the RFP.
B. Meet with the client anyways.
C. Suggest a project kick off meeting with a wider group of project stakeholders.
D. Hold a user survey with teachers, staff, and students.
We're bringing you a clip from ARE Live featuring a PcM Mock Exam question!
🔍 Scenario: Your firm is planning for their upcoming fiscal year and estimates that they need to secure 1-3 additional projects to meet the firm’s revenue goals.
Which of the following is not an appropriate way to learn about new projects?
A. Contacting previous clients about potential new work that does not yet have an RFP.
B. Meeting with local architecture firms for opportunities to partner on project types which your firm currently does not have experience in.
C. Attending a networking event with contractors to establish relationships for upcoming design-build projects.
D. Meeting with government officials to gain insight into several upcoming RFQs.
Dive into over 65 new lecture videos complete with brand new 3D models and scenarios that follow a real firm, OTJ Architects. Available now for all members!
#architecture #PA #programmingandanalysis #NCARB #areexams #areexam
Join Black Spectacles and architect Marissa Yee to learn the best study strategies for passing the PcM exam.
On this episode of ARE Live, we walk through a mock exam for the Practice Management division of the ARE 5.0. You'll learn about the PcM exam and we'll cover topics related to business development and project acquisition, proposal writing and project selection, client interaction and project initiation and more!
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
Timestamps:
04:10 Question No. 1
04:58 Answer for No. 1
8:58 Question No. 2
9:50 Answer for No. 2
14:55 Question No. 3
15:41 Answer for No. 3
19:00 Question No. 4
19:36 Answer for No. 4
23:50 Question No. 5
24:36 Answer for No. 5
🔍 Scenario: The design team is approaching 100% CDs and performs an in-house QA/QC. During this session, the reviewer discovers a non-compliant condition at the straight ramp in front of the building – there is not enough length at the bottom landing. The ramp is currently 32’ long and is already at maximum slope.
What should the architect do?
A. Remove the intermediate landing to reduce the ramp length.
B. Provide a switchback landing.
C. Extend the ramp to decrease slope.
D. No action required.
Which of the following are feasible options?
A. Penny tile: $6.30 / ft2
B. Large format tile: $6.10 / ft2
C. Penny tile: $5.90 / ft2
D. Large format tile: $5.70 / ft2
We're bringing you a clip from ARE Live featuring a PDD Mock Exam question!
🔍 Scenario: The architect is designing a new community center in Wisconsin. It is a one-story concrete slab-on grade building. At the end of 100% DD, the client reviews the documents. They then inform the architect that they plan to bring freestanding digital displays from the nearby community center into this facility, and locate them in the center of the lobby. The digital displays are approximately 24”x24”x48” tall.
Which disciplines will need to be coordinated? Select the two that apply.
A. Structural
B. Mechanical
C. Electrical
D. Plumbing
E. Civil
F. Landscape
We're bringing you a clip from ARE Live featuring a PDD Mock Exam question!
🔍 Scenario: The architect is designing a two-story office workplace and has just completed 50% CDs. At that time, the client informs the architect that they would like to change three rooms that are currently conference rooms into private offices. The area of those rooms are 150 ft2 each and are considered unconcentrated assembly space.
How will this affect the overall occupant load?
A. Decrease by 9 occupants.
B. Decrease by 27 occupants.
C. Increase by 9 occupants.
D. Increase by 27 occupants.
On this episode of ARE Live, we walk through a mock exam for the Project Development & Documentation division of the ARE 5.0. You'll learn about the PDD exam and we'll cover topics related to coordinating disciplines for center displays, addressing non-compliance issues in ramp design, meeting requirements for lighting and more!
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
Timestamps:
04:04 Question No. 1
04:56 Answer for No. 1
10:28 Question No. 2
10:59 Answer for No. 2
13:30 Question No. 3
14:16 Answer for No. 3
19:50 Question No. 4
20:48 Answer for No. 4
23:33 Question No. 5
24:34 Answer for No. 5
Learn more about Black Spectacles study materials at blackspectacles.com
On this episode of ARE Live, we walk through a mock exam for the Construction & Evaluation division of the ARE. You'll learn about the CE exam and we'll cover topics related to understanding your role during the bidding process, addressing safety concerns onsite and implications of paying or withholding certificates of payment.
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
Timestamps:
04:26 Question No. 1
06:22 Answer for No. 1
09:36 Question No. 2
10:18 Answer for No. 2
13:18 Question No. 3
15:08 Answer for No. 3
17:18 Question No. 4
19:47 Answer for No. 4
Learn more about Black Spectacles study materials at blackspectacles.com
👇 Drop your answer - A, B, C or D - in the comments!
🔍 Scenario: The architect notices that the stone consultant hasn’t issued their Commercial General Liability policy with the proper limits. When the architect approaches the issue, the stone consultant says they aren’t required to carry the monetary limits the architect is referring to.
How should the architect respond?
A. Give notice that the architect will need to terminate their services.
B. Provide the section of the contract that outlines insurance requirements.
C. Since the contract doesn’t include insurance requirements, reach out to the consultants insurance company for additional information.
D. The consultant does not need to disclose this information.
Clip from ARE Live: Project Planning & Design Mock Exam | ARE 5.0 PPD Exam (youtube.com/watch?v=VrmsB1JNqNY&ab_channel=BlackSpectacles)
👇 Drop your answer - A, B, C or D - in the comments!
🔍 Scenario: The client developing the new apartment building would like a sustainable building with optimized systems on a controlled budget where every system is selected based on cost, efficiency and sustainability.
Which water heating system is the most appropriate for the new apartment building?
A. Single electric resistance tank with multiple water storage tanks
B. Heat Recovery Systems located near exhaust vents
C. Central solar water heater with decentralized tankless heating coils
D. Single gas tank with recirculating pump
Clip from ARE Live: Project Management Mock Exam | ARE 5.0 PjM Exam (youtube.com/watch?v=HhIXnSTBfAo&ab_channel=BlackSpectacles)
🔍 Scenario: The mechanical engineer for the project is working towards their design development set when the structural engineer flags that one of their ducts is too large to penetrate a beam at the depth noted in the structural drawings. The mechanical engineer insists the deadline is too near to coordinate this item, and ignores the structural engineers request.
There are 2 weeks before the DD submission, how should the architect advise the team to proceed?
A. The mechanical engineer is justified and this should be coordinated in CD documents based on the time constraint.
B. The Architect should advise the structural engineer that this should have been flagged sooner and delay the DD submission as needed.
C. Remind the structural engineer that they are required to coordinate with other consultants, and given that there are 2 weeks until the deadline, this leaves adequate time.
D. The mechanical engineer is not required to coordinate with the structural engineer – this is the role of the architect.
👇 Drop your answer - A, B, C or D - in the comments!
Clip from ARE Live: Project Planning & Design Mock Exam | ARE 5.0 PPD Exam (youtube.com/watch?v=VrmsB1JNqNY&ab_channel=BlackSpectacles)
👇 Drop your answer - a Central System or Local System - in the comments!
🔍 Scenario: A big company wants to renovate and expand an existing building located in Arizona. The client wants to foster sustainable economic development with this expansion. The building will be designed as a Type B occupancy per IBC 2018 with a total occupant load of 540 distributed along multiple offices in 5 level.
What would be the most appropriate system: Central or Local System?
Clip from ARE Live: Project Management Mock Exam | ARE 5.0 PjM Exam (youtube.com/watch?v=HhIXnSTBfAo&ab_channel=BlackSpectacles)
🔍 Scenario: An architect has hired a landscape architect under the C401 agreement. The owner has provided the lot description, including the property line extents and siting of the building. The consultant requests a topographic survey for studying drainage patterns and informing the placement of landscape elements.
How should the Architect respond?
A. The owner provided adequate information, so this is not required for the landscape architect to fulfill their tasks.
B. This request is reasonable, and the consultant should reach out to the owner directly to obtain the survey.
C. The Architect should request a topographic survey from the client.
D. The Architect should request a topological survey from the client and bill the consultant for the cost incurred by the owner.
👇 Drop your answer - A, B, C or D - in the comments!
On this episode of ARE Live, we walk through a mock exam for the Project Planning & Design division of the ARE. You'll learn about the PPD exam and we'll cover topics like understanding how to integrate building systems in the project design.
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
Timestamps:
04:48 Question No. 1
05:30 Answer for No. 1
07:11 Question No. 2
08:20 Answer for No. 2
18:18 Question No. 3
18:44 Answer for No. 3
21:08 Question No. 4
21:45 Answer for No. 4
28:40 Question No. 5
29:10 Answer for No. 5
Learn more about Black Spectacles study materials at blackspectacles.com
On this episode of ARE Live, we walk through a mock exam for the Project Management division of the ARE. You'll learn about the PjM exam and we'll cover topics like understanding the intricacies of architect & consultant agreements and how these agreements relate to AIA contracts.
See previous episodes or register for the next ARE Live at blackspectacles.com/podcast
Timestamps:
07:05 Question No. 1
08:06 Answer for No. 1
12:13 Question No. 2
13:05 Answer for No. 2
16:27 Question No. 3
17:58 Answer for No. 3
20:03 Question No. 4
22:10 Answer for No. 4
Learn more about Black Spectacles study materials at blackspectacles.com
Our interface matches the real ARE 5.0 exam so you can get comfortable with the tools and study the material at the same time.
Plus each answer, whether you got it right or wrong, has an in-depth explanation so you can fully understand the concept behind each question.
Maximize your membership by combining practice exams with our other study materials. Start practicing today!
Each card is tailored to specific topics on the ARE and works seamlessly on your phone or computer.
Easily track and search key terms plus if you can't find what you need, you can create your own custom cards.
Get the most out of your membership by combining flashcards with our other study materials. Use code SPRING20 to save 20% on yearly subscriptions!
For every friend you refer who signs up for a membership: we'll give you $50 in your gift card of choice and we'll give your friend 10% off their subscription.
To participate, head over to blackspectacles.com/referral and start earning rewards today!
Use code SPRING20 to save 20% on yearly subscriptions: blackspectacles.com/pricing
You can find the Mock Exam link in our ARE Community by going to community.blackspectacles.com/t/are-live-pjm-case-study/4778/3
If you learn best by working through tough problems in real time with others, then we encourage you to try our Virtual Workshops, available with our Expert membership. Go to go.blackspectacles.com/pricing to get started. If you’re already a subscriber, you can upgrade to an Expert membership by logging into your account and clicking “manage subscription.”